Appendix 211. VESTING PERIODS AND EXPIRATION DATE OF PLAT APPROVALS


Latest version.
  • Preliminary Plat

    A Preliminary Plat for a subdivision shall be vested for a period of three (3) years from the date of Planning Commission approval.

    If all necessary permits are secured, site preparation commences, and Final Plat approval is obtained within the three (3) year vesting period following approval of the Preliminary Plat, then the vesting period shall be extended an additional two (2) years beyond the expiration of the initial three (3) year vesting period. During the two (2) year period the applicant shall commence construction and maintain any necessary permits to remain vested.

    If all necessary permits are not secured, site preparation does not commence, and Final Plat approval is not obtained within the three (3) year vesting period from the approval date of the Planning Commission then the vesting period shall expire and Preliminary Plat approval expires three (3) years from approval by the Planning Commission.

    Multi-Phase Developments

    In the case of developments which proceed in two (2) or more sections or phases as described on the Preliminary Plat there shall be a separate vesting period applicable to each section or phase. The development standards which are in effect on the date of approval of the Preliminary Plat for the first section or phase of the development shall remain the development standards applicable to all subsequent sections or phases of the development, provided the total vesting period for all phases shall not exceed fifteen (15) years from the date of the approval of the Preliminary Plat for the first section or phase, unless the City of Lakesite grants an extension, provided further that the applicant maintains any necessary permits during the fifteen (15) year period.

    Final Plat

    Approval of Final Plats shall expire after two (2) years from the date of approval by the Planning Commission.

(Added 12/8/14)